From Australia to the UK - our first South St project lands in London.

South.St

South St approached us over the Christmas break with an urgent requirement to support the delivery of their first UK retail space.

With an established store concept from their Australian locations, they needed our expertise to bring the design to life at London Westfield.

The key challenge was the ambitious handover timeline — just twelve weeks from sign-off to completion — but we were ready to rise to the occasion.

_Site Survey

_Technical Development

_Project Management

_Production

_ Installation

Installation

The installation process involved several key steps. First, we stripped out the existing fixtures and brick cladding, and completed the first fix electrical work. Next, we constructed the fitting rooms and carried out general repairs. Following that, we handled the decoration and completed the second fix electrical work. We then installed all the new fixtures and furniture, ensuring everything was in place and functioning. Finally, we conducted thorough quality checks before handing over the space to ensure everything met our high standards.

Bespoke Production

We were responsible for the bespoke production of various elements, including stainless steel doors and facade, black powder-coated hanging rails, and solid concrete rail blocks. Additionally, we created a sales counter with a stainless steel effect laminate, edge-lit mirrors, and a custom TV frame and plinth. To enhance the visual appeal, we designed LED-lit shelves and a feature panel, along with fitting room curtains and rails. Finally, we produced both internal and external signage to complete the overall design and branding of the space.

Project Management & Validations

We managed the entire project from start to finish, overseeing all contractors and suppliers while coordinating logistics. We ensured the necessary paperwork was provided, including RAMS, insurance, technical drawings, RD1-RD4, O&Ms, and As-Built Drawings upon project completion. To secure South St's consent to trade, we worked closely with Westfield, providing the required certifications, which included Building Control, Electrical, Fire Safety (including Fire Stopping), HVAC, Sprinkler, and Water Chlorination.

+
DRAG
EXPLORE
SHOWCASE
EXPLORE
SHOWCASE

Budget

£155k+

Overall budget was circa £155k.

Installation duration

4 weeks

We were on site for a total of 4 weeks.

.

.

"Bobblehat Interiors made my dream store come true. Our Stratford Westfield store that Bobblehat constructed is our first store outside of Australia & they made the whole process easy for us despite the time differences between the countries & our lack of knowledge in a foreign country. Their communication was perfect and overall really, really nice guys to work with. Our store fit out had a really tight deadline until we needed to be open and Bobblehat rose to the challenge and we opened in time. The look of the store speaks for itself - it's immaculate. We've had a few issues come up that's normal with a new fit out but Bobblehat have always been willing to come back & sort it out. 10/10 would recommend Bobblehat & we would work with them again for sure"

Harley Rae Booth

Owner

More Images

No items found.

Bobblehat's Capabilities Deck...

If you'd like to receive our capabilities deck pdf, please leave your details and we will send it to you.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
01
home
02
about
03
work
04
Services
05
news
06
testimonial
06
gallery
06
contact